To build a house in Toronto you move through seven stages in a fixed order: choose how you will build, confirm the lot can take the house, set a full budget, design and engineer it, get approvals and permits, build through the City's mandatory inspections, then close out with occupancy and warranty enrolment. Most delays and budget surprises come from doing these out of order, usually designing before zoning is checked. This guide walks through each stage with the current rules, fees and the questions to settle before you move on. If you would rather hand the whole process to one team, our custom home builder in Toronto service covers design, permits and construction under one contract.
Legislated review time for a complete new house permit
2026 permit fee for a new house, plus $56.33 per unit
Trunk diameter that makes a private tree protected
Tarion coverage on major structural defects in a contract home
Toronto changed several parts of the process this year. If you started planning before 2026, check these first.
New fees:Building permit and Committee of Adjustment fees were reset on January 1, 2026 (figures in Step 4).
Online-only permits:Since January 12, 2026, new house permits and the plumbing, mechanical and demolition permits tied to them must be filed through Toronto Building Online Services.
Lower development charges, with conditions:In July 2026 Council approved time-limited cuts of up to 60% for new housing under the Development Charges Reduction Program, subject to a transfer payment agreement with Ontario (details in Step 2).
Stronger tree rules:Since September 1, 2026, healthy private trees over 61 cm can be identified as Distinctive Trees, which get added protection when you apply to injure or remove them.
00
Three decisions shape everything after them, so settle them before you pay for drawings.
Who builds the house: In Ontario, anyone who builds a new home under contract for a landowner must be licensed by the Home Construction Regulatory Authority (HCRA) as both a builder and a vendor, and the home must be enrolled with Tarion before the contract is signed. You have three routes.
Design-build contract home
Architect plus general contractor
Owner-builder
An owner-builder who builds for their own use does not need an HCRA licence, but the house is not enrolled with Tarion, so you carry the defect risk yourself.
What land you build on: A knock-down rebuild on a lot you already own skips the land purchase but adds a demolition permit and demolition control rules. A vacant or severed lot needs servicing and often more zoning review. If you are still weighing whether to keep the existing house, read tear-down or renovate first.
How many units: Toronto now allows a duplex, triplex or fourplex as-of-right in residential zones across the city, and up to six units in the Toronto and East York district and Ward 23. A new build is the cheapest moment to add a unit, and units 2 to 4 on a residential parcel are exempt from development charges. Our guide to multiplex zoning eligibility in Toronto covers the unit rules.
01
Feasibility answers one question: can this lot legally and physically take the house you want? Every item below can change the design, so check them while the house is still a list of needs, not a set of drawings.

New build on Hanna Road, Leaside.
Zoning: Most of the city falls under Zoning By-law 569-2013, but some lots in Etobicoke, North York and Scarborough are still governed by former municipal by-laws (they show in grey on the City's interactive zoning map). Your zone label sets the limits. A label such as RD (f18; a707) means a residential detached zone with an 18 m minimum frontage and a 707 m² minimum lot area. Height, setbacks, lot coverage, floor area and building depth all come from the zone and any exception that applies to the lot.
Zoning Applicable Law Certificate (ZAP): Toronto will not treat a new house permit as complete without an issued ZAP, and the 10-day review clock does not start until the application is complete. The ZAP costs $644.38 for a new house and the City recommends getting it before you file with the Committee of Adjustment.+
Trees: Any private tree with a trunk of 30 cm or more in diameter is protected, and so are City street trees of any size. The permit application has to account for every protected tree your work could damage, which can include a neighbour's tree near the lot line. A tree inside the footprint or close to the excavation can move the house, change the basement or add months to the schedule. An arborist report at this stage costs far less than a redesign later.
Ravines and natural features: If the lot touches a ravine-protected area, you need a separate permit under the Ravine and Natural Feature Protection By-law to injure or remove trees, place fill or change grades, and the ravine line must appear on the survey and every plan. Our article on building on an infill or ravine lot in Toronto goes through these lots in detail.
Heritage: A designated property, or one inside a Heritage Conservation District, needs heritage review before demolition or new construction. That review can decide the massing and materials of the new house.
Demolition control: If you are replacing a house, Toronto expects the new house to be substantially complete within two years of demolition. If it is not, the City can add $20,000 per demolished unit to the property tax roll.
For a fuller lot checklist, see our guide on whether your Toronto lot is right for a custom home.
02
A Toronto custom house budget has five layers. Pricing only the construction leaves out the City charges, soft costs and contingency, and on a new single house the development charge alone can exceed $130,000.
Sources: City of Toronto fee schedules effective January 1, 2026; City of Toronto development charge rates effective June 26, 2025; Altus Group 2026 Canadian Cost Guide. Hard cost range excludes land, HST and soft costs.
A 3,000 sq ft custom house at the Altus range is about $1.5 million to $3.39 million in hard cost. If its gross floor area is about 300 m², the building permit fee is about $5,624 (300 × $18.56, plus one $56.33 unit fee).
Development charge per single or semi-detached house, City of Toronto.
Development charges: These are the largest City charge on a new house. The full rate for a single or semi-detached house is $137,846. Under the Development Charges Reduction Program, Council approved a 60% cut for singles and semis, to $55,138, where the first building permit is issued between March 30, 2026 and three years after the program's transfer payment agreement takes effect. For a new freehold house the charge is paid in full before occupancy. The City's development charge rules also list credits for redevelopment of land, so if your house replaces an existing one, ask Toronto Building to confirm what credit applies before you fix the budget.
HST rebates: If you build on land you own, you may qualify for the GST/HST new housing rebate for an owner-built home, which you apply for through the Canada Revenue Agency after construction is complete. Ontario's part of the rebate is up to $24,000, and a separate first-time home buyer rebate has been proposed. Confirm eligibility with your accountant before you count it in the budget.
Financing: Construction loans usually release money in draws as stages are inspected, so your cash flow has to cover each stage before the next draw arrives.
Our separate guide to the cost of custom home building in Toronto breaks the construction cost into trades and finishes.
03
Design turns the feasibility limits and the budget into a permit-ready drawing set. A new house can be designed by an architect, a professional engineer, or a designer qualified and registered under the Ontario Building Code (BCIN); the designer's registration details go on the drawings and the Schedule 1 form.
Expect three rounds:
Round 1: Concept
Layout and massing inside the zoning envelope
Round 2: Design development
Structure, mechanical systems, windows and materials
Round 3: Construction drawings
The permit set
Price checks at the end of each round keep the design inside the budget set in Step 2.

What Toronto Building expects in a new house permit set:
Engineer-sealed review: As expanded on July 14, 2025, when the drawings for a new house carry a professional engineer's seal, Toronto Building runs an expedited review that relies on that seal for Building Code compliance. It is worth asking your design team whether the drawings can be prepared for this route.
If you want one team to prepare the drawings and file everything with the City, see our architectural drawings and permit coordination service.
04
Approvals run in a set order: anything that changes what zoning allows comes first, then the permits that let you demolish and build.
Committee of Adjustment minor variance
When: The design breaks a zoning limit
Tree permit (Urban Forestry)
When: Work could injure or remove a protected tree
Ravine permit
When: Work in a ravine-protected area
Demolition permit with replacement building
When: You are replacing an existing house
New house building permit
When: Always
Plumbing, drain and HVAC permits
When: Always
Sources: City of Toronto Committee of Adjustment fees effective January 1, 2026; Toronto Building new house and demolition permit guides; Building Code Division C, Table 1.3.1.3.

Committee of Adjustment: If the design needs a variance, you apply by email to the Committee of Adjustment for your district, post a notice sign on the property at least 10 days before the hearing, and attend a public hearing where neighbours can comment. The Committee's business standard is 60 days for a minor variance, but the City's own 2025 review found average timelines remain well above that. Decisions can be appealed to the Toronto Local Appeal Body (TLAB), which adds months if it happens. The cheapest variance is the one you design out in Step 3.+
Tree permits: A permit to injure or remove a protected tree is usually issued conditional on the building permit. Trees over 61 cm may be identified as Distinctive Trees, and the City can refuse their removal.+
Building permit: The Building Code gives Toronto 10 business days to issue or refuse a complete house application, and a complete application needs the signed form, the drawing set, an issued ZAP and all fees paid. The 10 days often slip in practice: a 2024 Auditor General review found 17 of 27 sampled complete applications (63%) missed their legislated time frame. Incomplete applications have no review deadline at all, so a missing ZAP or drawing can stall the file indefinitely.
For the full list of approvals and how they stack, read what permits are needed to build a custom home in Toronto.
05
Before work starts, the site needs a construction fence and the Residential Infill Public Notice, a City-issued sign with your project details, posted where the street can see it. Construction noise is allowed from 7 a.m. to 7 p.m. on weekdays and 9 a.m. to 7 p.m. on Saturdays, with none on Sundays or statutory holidays.
A new house is built in this sequence, and Toronto Building inspects at each stage marked below. You or your builder must book each inspection; covering work before it is inspected can mean opening it up again. The inspections are included in the permit fee.

Demolition and site preparation
Services disconnected, house removed, excavation
Foundations
Footings, foundation walls, damp-proofing, drainage
Structure
Floor systems, walls, roof, windows
Rough-ins
Plumbing, HVAC, electrical, fireplaces and gas appliances

Envelope
Insulation, vapour barrier, air sealing
Finishes
Drywall, millwork, flooring, fixtures, exterior cladding
Occupancy
Required fixtures and life safety items in place
Completion
Remaining fixtures, grading, landscaping
Source: Toronto Building, inspections for small buildings and houses (Ontario Building Code Part 9). Your inspector confirms the exact list for your permit. Photos: framing stage (Unsplash, free licence); finished interior by Select Design Build.
Changes during construction: Any change to the permit drawings, such as moving a wall, changing a beam or adding a window, needs a revision filed with Toronto Building. Agree how changes are priced and approved in your contract before the build begins, because change orders are where most budget creep happens.
06
You cannot move in until the City is satisfied that the house is safe to occupy. In order:
Occupancy inspectionToronto Building confirms the house meets the Ontario Building Code requirements for occupancy. Moving in early requires a partial occupancy permit.
Development chargesFor a new freehold house, development charges are paid in full before occupancy.
Lot grading certificateYour lot grading consultant confirms final grades to Toronto Building once they are complete.
Final inspectionThis closes the permit. An open permit can complicate a future sale or your next permit application.
Rebate claimIf you qualify for an owner-built home rebate, apply after construction is complete.
When a licensed builder builds on your land, the home is covered by Tarion's statutory warranty, including coverage for major structural defects for 7 years from possession, up to $400,000. If the builder fails to substantially perform the contract, you may be entitled to financial loss protection of up to $40,000. An owner-built home has no Tarion coverage.+
Adding up the stage ranges below, a custom house in Toronto takes roughly 11 to 20 months from first meeting to move-in when no variance is needed, and longer when it is (our estimate). The approval stage is the hardest part to predict, because it depends on whether you need a variance and whether anyone appeals.
Sources: Select Design Build typical project ranges; City of Toronto and Building Code time frames. Ranges are typical, not guaranteed.
Builder column highlighted. Grey marks mean no role at that step.
Survey and arborist report
Zoning review and ZAP
Variance application
Structural and mechanical design
Permit application
Inspections
Warranty
Yes. If you own the land and build the house for your own use, you can act as an owner-builder without an HCRA licence. You still need every permit and inspection, and the house will not have Tarion warranty coverage.
It depends on the lot. If you already own the land, building lets you spend on the house rather than on a seller's land price, but you also carry design fees, City charges and the cost of living elsewhere during the build. Compare the full five-layer budget in Step 2 with the price of a comparable new house on the market.
Not always. A house can be designed by an architect, a professional engineer, or a designer registered under the Ontario Building Code (BCIN). The structural design must still be done by someone qualified for it, and many projects use an engineer for structure either way.
Yes. A house replacement uses the Residential Demolition Permit with Replacement Building, filed with the new house permit, and you sign an acknowledgement of the City's demolition control conditions.
In most residential zones you can build up to four units as-of-right, and up to six in the Toronto and East York district and Ward 23, subject to the zone's size limits. Units 2 to 4 are exempt from development charges.
November 25, 2026: First published. Includes 2026 permit and Committee of Adjustment fees, online permit filing, the Development Charges Reduction Program and the September 2026 tree by-law changes.